Fairfax Blvd at Chain Bridge Rd Intersection (Northfax)

Print

Northfax Intersection

Project Description:

  • Provide road improvements on Chain Bridge Road (Route 123) from Route 29/50 (Fairfax Boulevard) to Eaton Place
  • Widen Chain Bridge Road (Route 123) to six lanes from Route 29/50 (Fairfax Boulevard) to Eaton Place
  • Improve the geometrics (lane alignments) of the roadway approaches for the intersection of Route 29/50 (Fairfax Boulevard) at Chain Bridge Road (Route 123)
  • Improve pedestrian accommodations at all legs of the intersection
  • Make extensive culvert improvements to eliminate roadway flooding caused by the inadequate culvert under Route 123

Project Schedule:

  • Construction Advertisement: Spring 2016
  • Construction Start: Summer 2016 - Summer 2018
  • Utility Relocation: Ongoing

Project Plans:

Documents for Download:

Northfax Construction Updates