Gateway Regional Park Renovation

  • Project typeCity Project
  • Project divisionCommunity & Development
  • Project scheduleUnder Construction
  • Contractor nameAvon Corporation
plans showing Gateway Park renovation

Project Description

The Gateway Regional Park Renovation project transforms the existing park into a resilient, environmentally focused public open space that enhances both ecological function and visitor experience. Central to the project is the creation of new wetlands designed to support improved water quality, habitat restoration, and nature-based learning. The renovation also improves accessibility and creates engaging recreational and educational experiences while encouraging stewardship of the park's natural resources.

Improvements include:

  • 48 new trees
  • 155 shrubs
  • Approximately 22,000 square feet of groundcovers
  • 297 Riparian Preservation Area (RPA) plantings that support biodiversity and restore native habitat
  • New trails and elevated boardwalks
  • Interpretive signage
  • Dedicated parking

As part of the construction process, approximately 80 trees will be removed beginning around July 1, 2026. This project is by-right and has completed the city's site plan approval process.

Project Status

Construction is underway. The project is being completed by Avon Corporation.

Project Timeline

  • April–May 2026: City Permits
  • June–September 2026: Construction
  • October–November 2026: Fall Planting
  • March–April 2027: Spring Planting

Project Background

Gateway Regional Park is managed by the Northern Virginia Regional Park Authority (NVRPA). The renovation supports regional flood mitigation efforts by increasing stormwater retention capacity and strengthening the site's overall ecological resilience, with enhancements to wildlife habitat through native planting strategies, invasive species management, and ecological restoration throughout the park.

"A Reimagined Gateway Park" is included on page 20 of the Fairfax Circle Small Area Plan.

City Council Presentations & Work Sessions

Location

Gateway Regional Park, 2823 Pickett Rd., Fairfax, VA 22030  View Map

Google Map